What challenges did we face?

This was a hugely complex project within Wellingborough’s largest strategic development.

Ground conditions and level differences on site meant a detailed earthworks operation was necessary, achieved concurrently with the installation of infrastructure.

Permanent retaining solutions were constructed in advance of the groundworks, foundations and substructure works to resolve this issue.

What we delivered

With the latest 3D machine control technology available, the in-house MIDA engineering department designed a bespoke earthworks model.

This allowed the site to progress permanent works, ensuring the delivery programme maintained the planned schedule.