Sawbridgeworth – Barratt Homes

  • Hertfordshire
  • Residential
  • Barratt Homes North Thames
Project Value
£12m
New Homes
200
Adoptable Carriageway
16,000m2
Adoptable Drainage
6000m
Concrete
9000m3

What challenges did we face?

The site had restricted access with a large off-site haul road – temporary access was successfully installed through third-party land.

On-site water levels were under constant pressure – this was overcome by constructing temporary holding ponds.

The built-up residential area required careful management, with deliveries and plant access carefully planned to reduce the disruption for residents and the local school.

What we delivered

Within 12 months of commencement, 90 new homes were completed, along with the adoptable infrastructures both on and off-site.

Pre-Development Assistance
Earthworks & Enabling Works
Infrastructure & Civil Engineering
Groundworks
Hard & Soft Landscaping
Pre-Development Assistance
Earthworks & Enabling Works
Infrastructure & Civil Engineering
Groundworks
Hard & Soft Landscaping

Since their introduction to our business, MIDA have grown to become one of our “go to” groundworks contractors.

Antonios Castro
Commercial Director