Mosaic House – Barratt Homes

  • Hemel Hempstead
  • Commercial & Industrial
  • Barratt Homes David Wilson
Project Value
£600,000
Construction Date
July 2022

What challenges did we face?

The project involved challenging remedial works in a complex residential environment, that was subject to public interfaces.

This was also coupled with access challenges, and unpleasant weather conditions caused by above-average temperatures.

What we delivered

We successfully carried out the remedial works, including detailed concrete work to a failed podium deck and the removal and replacement of a new proprietary waterproof system.

The project also included the removal and reinstatement of the landscaped areas.

MIDA Civil Engineering provided dynamic engineering solutions and delivered a quality service.

Tom Slater
Senior Technical Manager, Barratt David Wilson Homes